The Project:
- Consented in 2016, the demolition of the existing Old Māngere Bridge and replacement with a new walking and cycling bridge represents Waka Kotahi NZ Transport Agency’s commitment to creating a safer and more accessible transport network
- The bridge crosses the Manukau Harbour between Onehunga and Māngere Bridge and will restore important community connections as well as become a destination in itself
- The new $38M, 258m bridge has an 8m wide deck consisting of approximately 23m spans including an arch supported central span of 60m
Resolve Group:
- Was Engineer to the Contract
- Undertook contract management for Waka Kotahi NZ Transport Agency