• Atiamuri Bridge Replacement
  • Atiamuri Bridge Replacement
  • Atiamuri Bridge Replacement
  • Replacement of existing steel arch bridge over Waikato River on SH1, 40km north of Taupo
  • New concrete & steel 4-stringer composite-deck bridge, realignment of 2.5km of SH1, relocation of SH1 & SH30 intersection, 1.5km of new northbound passing lane & facilities for the Waikato River Cycleway over bridge
  • Procured under NZTA’s Early Contract Involvement (ECI) Model & arguably NZTA’s most successful ECI to date
  • Negotiation, Contract Administration & Construction Management of the $24m Design & Construct (D&C) Project awarded to HEB Construction
  • New alignment of SH1 & SH30 & new bridge of the Waikato River opening to public traffic on 18 March 2013
  • Old steel arch bridge dismantled
  • Open to traffic on 16 March, 2013